Project Detail
Residential Development of 20 dwellings
Date
Completed January 2007
Project Cost
£1.7m
Key Site Issues
Brownfield site in residential area
Contaminated land
Project Detail
Re-development of former Charles Andrew Clinic
for residential housing (70 units)
Date
April 2007 - present
Project Cost
£5m
Key Site Issues
Brownfield site in residential area
Contaminated land
Former mining activity
Project Detail
Re-development of former ironworks site
and adjacent disused garage
Date
Oct 2007 - present
Project Cost
£3.5m
Key Site Issues
Brownfield site in residential area
Contaminated land
Culvert crossing
Flooding
Adjacent to watercourse